Glossary
Construction completions glossary, in plain words
The terms you'll meet between the last weld and the signed handover certificate, explained in a sentence or two.
A
- As-built drawings
- As-built drawings show what was actually built, including changes made during construction, and are handed over to operations at the end of a project.
C
- Check sheet (ITR)
- A check sheet, or inspection and test record (ITR), is the form that proves one tag was installed or tested correctly, line by line, with readings checked against acceptance limits.
- Commissioning
- Commissioning is the process of starting up and testing systems so they work together as designed, from functional tests and solo runs to performance tests.
E
- Equipment preservation
- Equipment preservation is the routine care stored and installed equipment needs before start-up, such as rotating shafts, running heaters and replacing desiccant, so it isn't damaged and warranties stay valid.
F
- Final acceptance certificate (FAC)
- A final acceptance certificate (FAC) confirms the client has accepted the finished work: all punch items and NCRs are closed and the final documentation is complete.
H
- Handover to operations (HO)
- Handover to operations is the formal transfer of custody of a system from the project to the operating team, with documents, spares and trained operators in place.
- Hold point
- A hold point is a step in an inspection and test plan where work must stop until the named party has inspected and released it.
I
- Inspection and test plan (ITP)
- An inspection and test plan (ITP) lists every inspection and test for a scope of work, the acceptance criteria, the record each step produces and who must hold, witness or review it.
- Issued for construction (IFC)
- Issued for construction (IFC) is the revision status that means a drawing or document is approved for building, after earlier issues for review (IFR) and approval (IFA).
J
- Job safety analysis (JSA)
- A job safety analysis (JSA) breaks a task into steps, identifies the hazards in each and sets controls before the work starts.
L
- Lock-out / tag-out (LOTO)
- Lock-out / tag-out (LOTO) is the procedure for isolating energy sources with locks and tags, and verifying the isolation, so equipment can't be started while people work on it.
M
- Management of change (MOC)
- Management of change (MOC) is the process for reviewing, approving and recording changes to design, equipment or procedures, so their safety, cost and schedule impacts are understood first.
- Mechanical completion (MC)
- Mechanical completion (MC) is the point where a system is built and installed to design, its construction checks are done and no Category A punch items or major NCRs are open.
N
- Nonconformance report (NCR)
- A nonconformance report (NCR) records work, material or equipment that doesn't meet the specification, and how it will be dealt with: use as is, repair, rework or reject.
P
- Permit to work (PTW)
- A permit to work is a written authorisation for high-risk work, such as hot work, confined space entry or electrical work, that sets out the hazards, controls, isolations and approvals.
- Pre-commissioning
- Pre-commissioning is the testing done after mechanical completion and before commissioning, without process fluids: cleaning, flushing, insulation resistance tests, loop checks and alignment.
- Punch category (A / B / C)
- Punch categories rank punch items by when they must be fixed: Category A before mechanical completion or energisation, B before handover, and C after handover.
- Punch list
- A punch list is the list of defects and unfinished work found during inspections near the end of construction, each of which must be fixed and verified before handover.
R
- Ready for commissioning (RFC)
- Ready for commissioning (RFC) means a subsystem has passed its pre-commissioning tests and is safe to start commissioning.
- Ready for start-up (RFSU)
- Ready for start-up (RFSU) means a system is commissioned, its safety systems are tested and it's ready to receive process fluids or be energised for operation.
- Rules of credit
- Rules of credit split an activity into weighted steps so partial work earns partial progress, for example a cable earning 40 % when pulled, 20 % per end terminated and 20 % when tested.
S
- Systemization (systems & subsystems)
- Systemization divides a facility into systems and subsystems that can be completed, tested and handed over one at a time, instead of all at once by area.
T
- Tag register
- A tag register is the list of every tagged item on a project, such as pumps, motors, instruments, valves and lines, with its type, subsystem and technical data.
- Technical query / RFI (TQ)
- A technical query (TQ), or request for information (RFI), is a formal question from site to engineering or the designer to clarify a drawing, specification or requirement.
- Turnover package
- A turnover package is the set of records handed over with a system: certificates, check sheets, punch lists, test records, NCRs, drawings and vendor documents.
W
- Walkdown
- A walkdown is a physical inspection of a system or area, usually with the contractor and owner, to find and record punch items before a completion milestone.
- Witness point
- A witness point is a step in an inspection and test plan that a named party is invited to attend, but work may continue if they don't come after proper notice.