Construction completions glossary, in plain words

The terms you'll meet between the last weld and the signed handover certificate, explained in a sentence or two.

A

As-built drawings
As-built drawings show what was actually built, including changes made during construction, and are handed over to operations at the end of a project.

C

Check sheet (ITR)
A check sheet, or inspection and test record (ITR), is the form that proves one tag was installed or tested correctly, line by line, with readings checked against acceptance limits.
Commissioning
Commissioning is the process of starting up and testing systems so they work together as designed, from functional tests and solo runs to performance tests.

E

Equipment preservation
Equipment preservation is the routine care stored and installed equipment needs before start-up, such as rotating shafts, running heaters and replacing desiccant, so it isn't damaged and warranties stay valid.

F

Final acceptance certificate (FAC)
A final acceptance certificate (FAC) confirms the client has accepted the finished work: all punch items and NCRs are closed and the final documentation is complete.

H

Handover to operations (HO)
Handover to operations is the formal transfer of custody of a system from the project to the operating team, with documents, spares and trained operators in place.
Hold point
A hold point is a step in an inspection and test plan where work must stop until the named party has inspected and released it.

I

Inspection and test plan (ITP)
An inspection and test plan (ITP) lists every inspection and test for a scope of work, the acceptance criteria, the record each step produces and who must hold, witness or review it.
Issued for construction (IFC)
Issued for construction (IFC) is the revision status that means a drawing or document is approved for building, after earlier issues for review (IFR) and approval (IFA).

J

Job safety analysis (JSA)
A job safety analysis (JSA) breaks a task into steps, identifies the hazards in each and sets controls before the work starts.

L

Lock-out / tag-out (LOTO)
Lock-out / tag-out (LOTO) is the procedure for isolating energy sources with locks and tags, and verifying the isolation, so equipment can't be started while people work on it.

M

Management of change (MOC)
Management of change (MOC) is the process for reviewing, approving and recording changes to design, equipment or procedures, so their safety, cost and schedule impacts are understood first.
Mechanical completion (MC)
Mechanical completion (MC) is the point where a system is built and installed to design, its construction checks are done and no Category A punch items or major NCRs are open.

N

Nonconformance report (NCR)
A nonconformance report (NCR) records work, material or equipment that doesn't meet the specification, and how it will be dealt with: use as is, repair, rework or reject.

P

Permit to work (PTW)
A permit to work is a written authorisation for high-risk work, such as hot work, confined space entry or electrical work, that sets out the hazards, controls, isolations and approvals.
Pre-commissioning
Pre-commissioning is the testing done after mechanical completion and before commissioning, without process fluids: cleaning, flushing, insulation resistance tests, loop checks and alignment.
Punch category (A / B / C)
Punch categories rank punch items by when they must be fixed: Category A before mechanical completion or energisation, B before handover, and C after handover.
Punch list
A punch list is the list of defects and unfinished work found during inspections near the end of construction, each of which must be fixed and verified before handover.

R

Ready for commissioning (RFC)
Ready for commissioning (RFC) means a subsystem has passed its pre-commissioning tests and is safe to start commissioning.
Ready for start-up (RFSU)
Ready for start-up (RFSU) means a system is commissioned, its safety systems are tested and it's ready to receive process fluids or be energised for operation.
Rules of credit
Rules of credit split an activity into weighted steps so partial work earns partial progress, for example a cable earning 40 % when pulled, 20 % per end terminated and 20 % when tested.

S

Systemization (systems & subsystems)
Systemization divides a facility into systems and subsystems that can be completed, tested and handed over one at a time, instead of all at once by area.

T

Tag register
A tag register is the list of every tagged item on a project, such as pumps, motors, instruments, valves and lines, with its type, subsystem and technical data.
Technical query / RFI (TQ)
A technical query (TQ), or request for information (RFI), is a formal question from site to engineering or the designer to clarify a drawing, specification or requirement.
Turnover package
A turnover package is the set of records handed over with a system: certificates, check sheets, punch lists, test records, NCRs, drawings and vendor documents.

W

Walkdown
A walkdown is a physical inspection of a system or area, usually with the contractor and owner, to find and record punch items before a completion milestone.
Witness point
A witness point is a step in an inspection and test plan that a named party is invited to attend, but work may continue if they don't come after proper notice.