What is a punch list?

A punch list is the list of defects and unfinished work found during inspections near the end of construction, each of which must be fixed and verified before handover.

Each punch item describes one problem at one location or tag, such as a missing cable gland or a damaged coating. It names the company responsible, a category that says how urgent it is, and who verified it once fixed.

Punch lists are usually built up during walkdowns of each system or area. Items move from open, to ready for verification once the contractor has fixed them, to closed once an inspector has checked them on site.

Open punch items roll up by subsystem: no top-category items may be open at mechanical completion, and all items must be closed before final acceptance.