What is a punch category (A / B / C)?

Punch categories rank punch items by when they must be fixed: Category A before mechanical completion or energisation, B before handover, and C after handover.

Category A items affect safety, integrity or function, so the system can't be completed or energised while they're open. Category B items must be fixed but don't stop commissioning. Category C items are minor or cosmetic.

Some projects use numbers (1 to 4) instead of letters. Whatever the scheme, agree the meanings with the client at the start and apply them consistently, because certificates depend on them.