What is systemization (systems & subsystems)?
Systemization divides a facility into systems and subsystems that can be completed, tested and handed over one at a time, instead of all at once by area.
Each tag belongs to one subsystem. Check sheets, punch items and certificates roll up by subsystem, which lets commissioning start on finished systems while construction continues elsewhere.