Tag register template (CSV)
The tag register is the backbone of completions: every pump, motor, instrument and line, with its type and subsystem. This CSV has the exact columns SureCon imports, so filling it in is the fastest way to start a project.
No sign-up or email needed.
Preview
The file's layout and first rows.
Tag register
| Tag | Type | Subsystem | Description | Discipline | Area | Company | Loop | Range | Signal | I/O | P&ID | Calibration due | Rated power |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 10-P-1001A | Centrifugal pump | 10-01 | Feed pump A | Mechanical | Unit 10 | Apex Mechanical | PID-10-001 | 55 kW | |||||
| 10-PM-1001A | Electric motor | 10-01 | Feed pump A motor | Electrical | Unit 10 | Volt Electrical | PID-10-001 | 55 kW | |||||
| 10-PT-1001 | Pressure transmitter | 10-01 | Feed pump discharge pressure | Instrumentation | Unit 10 | Volt Electrical | L-1001 | 0–25 barg | 4–20 mA | AI | PID-10-001 | 2027-06-30 | |
| 10-FV-1002 | Control valve | 10-01 | Feed flow control valve | Instrumentation | Unit 10 | Volt Electrical | L-1002 | 0–100 % | 4–20 mA | AO | PID-10-001 | ||
| 10-SWB-01 | Switchboard | 10-02 | LV switchboard 1 | Electrical | Substation 1 | Volt Electrical | |||||||
| 10-L-1001 | Piping line | 10-01 | Pump discharge line | Piping | Unit 10 | Apex Mechanical | PID-10-001 |
What's inside
- All the columns SureCon imports, in the right order
- Six example tags across mechanical, electrical, instrumentation and piping
- Extra columns (e.g. Rated power) become technical data on the tag
How to use it
- 1Keep the header row; replace the example tags with yours.
- 2Tag, Type and Subsystem are required on every row.
- 3Use the tag types listed on this page to get check sheets automatically.
- 4In SureCon: Tags → Import CSV. Re-importing updates existing tags.
Tag types SureCon recognises
Use these in the Type column and each tag gets its check sheets automatically.
- Centrifugal pump
- Electric motor
- Pressure transmitter
- Flow transmitter
- Control valve
- Switchboard
- Piping line
- Storage tank
- Transformer
- Power cable
- Earthing system
- Heat tracing circuit
- Lighting circuit
- Fire & gas detector
- Pressure safety valve
- Manual valve
- HVAC unit
- Duct
- Foundation
- Steel structure
- Telecom device
Questions
Which columns are required?
Tag, Type and Subsystem. Everything else is optional, and any extra column becomes technical data on the tag.
Which tag types does SureCon recognise?
Centrifugal pump, Electric motor, Pressure transmitter, Flow transmitter, Control valve, Switchboard, Piping line, Storage tank, Transformer, Power cable, Earthing system, Heat tracing circuit, Lighting circuit, Fire & gas detector, Pressure safety valve, Manual valve, HVAC unit, Duct, Foundation, Steel structure, Telecom device. Each gets its check sheets and deliverables automatically.
Mechanical completion and handover, worked out from your records
Same layout, but on a phone, with photos, sign-offs and live progress for the whole team. Free, with unlimited users.