Commissioning readiness checklist
Use it before each subsystem moves from construction to commissioning. If every box is ticked, the commissioning team can start without surprises.
No sign-up or email needed.
Preview
First of 3 sheets: Construction, Testing & documents, Safety & people
Construction complete
| Done | Item | Evidence / notes |
|---|---|---|
| [ ] | Mechanical completion certificate signed | |
| [ ] | All construction (A) check sheets signed and verified | |
| [ ] | No open category A punch items | |
| [ ] | Walkdown done with commissioning and the client; findings punched |
What's inside
- 12 readiness items in three sections
- A tick box and an evidence column for each item
- Fits on one printed page
How to use it
- 1Print one per subsystem and write the subsystem number at the top.
- 2Tick each item only with evidence: a certificate number, test pack or record.
- 3Hold the walkdown and the operator briefing on site; the rest can be checked in the system.
Questions
What does ready for commissioning mean?
Construction is complete and checked, pre-commissioning tests are done and recorded, and the system is safe to energise or fill under the commissioning team's control.
Who signs off commissioning readiness?
Usually the construction and commissioning leads together, often witnessed by the client, against the agreed certificate prerequisites.
Mechanical completion and handover, worked out from your records