Free Excel template
Check sheet (ITR) templates
Inspection and test records (ITRs), or check sheets, prove each tag was installed and tested correctly. This workbook holds SureCon's standard library: A-sheets for construction, B-sheets for pre-commissioning and C-sheets for commissioning, with acceptance limits on every reading.
No sign-up or email needed.
Preview
First of 39 sheets: Index, C-A01, E-A01, E-A02, E-A03, E-A04…
Check sheet (ITR) templates
| Code | Title | Phase | Used for tag types |
|---|---|---|---|
| C-A01 | Foundation & grout check | A: Construction | Foundation |
| E-A01 | Motor installation check | A: Construction | Electric motor |
| E-A02 | Cable installation & termination | A: Construction | Electric motor, Power cable |
| E-A03 | Switchboard installation check | A: Construction | Switchboard |
| E-A04 | Transformer installation check | A: Construction | Transformer |
| E-A05 | Lighting & small power installation | A: Construction | Lighting circuit |
| E-A06 | Heat tracing installation (3-stage insulation test) | A: Construction | Heat tracing circuit |
| E-B01 | Motor insulation resistance test | B: Pre-commissioning | Electric motor |
+ 30 more rows in the file
What's inside
- 37 templates, one per sheet, with checks and readings
- Acceptance limits for readings such as alignment and insulation resistance
- Index of which tag types use which sheets
- Header block and sign-off for each sheet
How to use it
- 1Find the sheets your tag type needs in the Index.
- 2Copy a sheet per tag and fill in the header.
- 3Record pass / fail / N/A and readings on site.
- 4Sign when every line passes; the inspector verifies.
Questions
What are A, B and C check sheets?
A-sheets cover construction and installation (towards mechanical completion), B-sheets pre-commissioning tests (towards ready for commissioning) and C-sheets commissioning (towards ready for start-up).
Are the acceptance limits right for my project?
They're typical values. Always check them against your project specifications and vendor data before use.
Can SureCon create these for every tag?
Yes. Import your tag register and SureCon creates the right check sheets for every tag, to fill in on a phone.
Digital check sheets and ITRs, filled in on a phone
Same layout, but on a phone, with photos, sign-offs and live progress for the whole team. Free, with unlimited users.