Free Excel template
Completion certificate templates (MC to FAC)
Five certificates take a subsystem from construction to the client: mechanical completion (MC), ready for commissioning (RFC), ready for start-up (RFSU), handover to operations and final acceptance (FAC). Each template lists the readiness checks and the sign-off chain SureCon uses.
No sign-up or email needed.
Preview
First of 5 sheets: MC, RFC, RFSU, HO, FAC
Mechanical Completion certificate
- Project
- System
- Subsystem
- Certificate number
- Date
- Meaning
- Built and installed as designed; construction checks done.
| No. | Readiness check | Met (Yes / No / N/A) | Evidence / reference |
|---|---|---|---|
| 1 | Construction (A) check sheets complete and signed | ||
| 2 | No open Category A punch items | ||
| 3 | Major and critical NCRs closed | ||
| 4 | Documents required for MC accepted |
What's inside
- MC, RFC, RFSU, handover and FAC certificates, one per sheet
- Readiness checks for each stage
- Sign-off chain from construction to client
- Header for system, subsystem and certificate number
How to use it
- 1Fill in the subsystem and certificate number.
- 2Check each readiness item and note the evidence.
- 3Attach the outstanding punch list allowed at this stage.
- 4Sign in order; each certificate needs the previous one.
Questions
What is a mechanical completion certificate?
It confirms a system or subsystem is built and installed to design, with construction check sheets complete and no top-category punch items or major NCRs open, so pre-commissioning can start.
Who signs the MC certificate?
Typically the contractor's construction manager and the owner's completions lead. Your contract may name others.