A nonconformance report records work, material or equipment that doesn't meet the specification and how it will be dealt with. This template gives you a one-page NCR form and a register to track every NCR to close-out.
No sign-up or email needed.
Preview
First of 2 sheets: NCR form, NCR register
Nonconformance report (NCR)
- NCR number
- Project
- Date raised
- Raised by
- Tag / area
- Subsystem
- Responsible company
- Severity
- Minor / Major / Critical
- Specification / drawing reference
| Section | Details |
|---|---|
| 1. Description of the nonconformance | What is wrong, against which requirement? |
| 2. Proposed disposition | Use as is / Repair / Rework / Reject / replace / Return to vendor |
| 5. Corrective action | What was done to fix this item? |
| 6. Preventive action | What stops it happening again? |
| 7. Verification | Checked on site by / date / result |
| 8. Close-out | Closed by / date |
+ 3 more rows in the file
What's inside
- NCR form with header, eight sections and sign-off
- Severity (minor / major / critical) and disposition options
- NCR register with 30 numbered rows
- The six-step NCR process, written out
How to use it
- 1Raise the NCR with the requirement it breaks.
- 2The responsible company proposes a disposition.
- 3Quality approves it; corrective action is done and recorded.
- 4Verify on site and close; update the register.
Questions
What are the disposition options for an NCR?
Commonly: use as is, repair, rework, reject / replace, or return to vendor. Use as is and repair usually need the designer's approval.
When must NCRs be closed?
Major and critical NCRs should be closed before mechanical completion, and all NCRs before final acceptance.