Inspection and test plan (ITP) template

An inspection and test plan lists every inspection and test for a scope, the acceptance criteria, the record each step produces and who holds, witnesses or reviews it. This template includes a worked example for an electrical installation that you can adapt.

No sign-up or email needed.

Preview

The file's layout and first rows.

Inspection and test plan (example: electrical installation)

Project
ITP number / revision
Discipline / scope
Electrical: LV motors, cables and switchboards
Contractor
Specifications
StepActivityReference / procedureAcceptance criteriaRecord (check sheet)ContractorOwnerThird partyRemarks
1Receiving inspection of motors and switchboardsPurchase order, datasheetNo damage; nameplate matches datasheetMaterial receiving recordHR
2Motor installation and alignmentInstallation procedureSecure, aligned, earthedE-A01 Motor installation checkHS
3Cable pulling and terminationCable schedule, termination procedureCorrect route, glands and lugs; ferrules fittedE-A02 Cable installation & terminationHWSample 10 %
4Switchboard installationGA drawing, vendor manualLevel, bolted, earthed, IP rating keptE-A03 Switchboard installation checkHW
5Motor insulation resistance testTest procedureIR ≥ limit on the check sheetE-B01 Motor insulation resistance testHWW
6Cable insulation and continuity testTest procedureIR and continuity within limitsE-B04 Cable insulation & continuity testHW
7Switchboard functional testVendor test procedureInterlocks and protections workE-B02 Switchboard functional testHHW
8Motor solo runCommissioning procedureRotation, current and vibration within limitsE-C01 Motor solo runHH

+ 1 more rows in the file

What's inside

  • ITP sheet with step, activity, reference, criteria, record and intervention columns
  • Worked example: 9 steps for LV motors, cables and switchboards
  • Legend for H (hold), W (witness), R (review) and S (surveillance)
  • Sign-off block: prepared, reviewed, approved

How to use it

  1. 1Fill in the scope, specifications and contractor.
  2. 2List each inspection and test in the order the work happens.
  3. 3Name the record (check sheet) each step produces.
  4. 4Agree the intervention points with the owner and third party, then approve.

Questions

What is the difference between a hold point and a witness point?

At a hold point, work must stop until the named party has inspected and released it. At a witness point they're invited to attend, but work may continue if they don't.

Who prepares the ITP?

Usually the contractor, for each discipline or scope. The owner's QA/QC reviews it and sets their own intervention points before approval.