Free Excel template
Inspection and test plan (ITP) template
An inspection and test plan lists every inspection and test for a scope, the acceptance criteria, the record each step produces and who holds, witnesses or reviews it. This template includes a worked example for an electrical installation that you can adapt.
No sign-up or email needed.
Preview
The file's layout and first rows.
Inspection and test plan (example: electrical installation)
- Project
- ITP number / revision
- Discipline / scope
- Electrical: LV motors, cables and switchboards
- Contractor
- Specifications
| Step | Activity | Reference / procedure | Acceptance criteria | Record (check sheet) | Contractor | Owner | Third party | Remarks |
|---|---|---|---|---|---|---|---|---|
| 1 | Receiving inspection of motors and switchboards | Purchase order, datasheet | No damage; nameplate matches datasheet | Material receiving record | H | R | ||
| 2 | Motor installation and alignment | Installation procedure | Secure, aligned, earthed | E-A01 Motor installation check | H | S | ||
| 3 | Cable pulling and termination | Cable schedule, termination procedure | Correct route, glands and lugs; ferrules fitted | E-A02 Cable installation & termination | H | W | Sample 10 % | |
| 4 | Switchboard installation | GA drawing, vendor manual | Level, bolted, earthed, IP rating kept | E-A03 Switchboard installation check | H | W | ||
| 5 | Motor insulation resistance test | Test procedure | IR ≥ limit on the check sheet | E-B01 Motor insulation resistance test | H | W | W | |
| 6 | Cable insulation and continuity test | Test procedure | IR and continuity within limits | E-B04 Cable insulation & continuity test | H | W | ||
| 7 | Switchboard functional test | Vendor test procedure | Interlocks and protections work | E-B02 Switchboard functional test | H | H | W | |
| 8 | Motor solo run | Commissioning procedure | Rotation, current and vibration within limits | E-C01 Motor solo run | H | H |
+ 1 more rows in the file
What's inside
- ITP sheet with step, activity, reference, criteria, record and intervention columns
- Worked example: 9 steps for LV motors, cables and switchboards
- Legend for H (hold), W (witness), R (review) and S (surveillance)
- Sign-off block: prepared, reviewed, approved
How to use it
- 1Fill in the scope, specifications and contractor.
- 2List each inspection and test in the order the work happens.
- 3Name the record (check sheet) each step produces.
- 4Agree the intervention points with the owner and third party, then approve.
Questions
What is the difference between a hold point and a witness point?
At a hold point, work must stop until the named party has inspected and released it. At a witness point they're invited to attend, but work may continue if they don't.
Who prepares the ITP?
Usually the contractor, for each discipline or scope. The owner's QA/QC reviews it and sets their own intervention points before approval.
Inspection and test plans, with hold and witness points that run themselves
Same layout, but on a phone, with photos, sign-offs and live progress for the whole team. Free, with unlimited users.