Is it ready for commissioning? A readiness checklist
What has to be true before a system is energised, flushed or started, and how to check it in minutes rather than days.
· 6 min read

Starting commissioning on a system that isn't ready wastes the commissioning team's time and can be dangerous. Use this checklist before each subsystem moves from construction to commissioning.
Construction
- Mechanical completion certificate signed.
- All construction (A) check sheets signed and verified.
- No open category A punches.
- Walkdown done with commissioning and the client, findings punched.
Testing and documentation
- Pressure tests done and test packs released for piping.
- Cable insulation and continuity tests recorded.
- Vendor manuals and commissioning procedures received and approved.
- Calibration certificates for instruments and test equipment current.
Safety and people
- System boundaries marked on drawings and on site.
- Isolation and permit arrangements agreed for the system.
- Operators and maintenance staff briefed.
- Preservation records up to date, with no open issues.
Checking it quickly
If the records are in one system, most of this checklist is a filter, not a hunt. Open the subsystem and look at its sheets, punches, test packs and certificate status on one page. The walkdown and the people items are the only ones that need someone on site.
In SureCon
The turnover tracker shows each subsystem's readiness, the ITR matrix shows sheet status by tag, and test packs, preservation and commissioning activities are all linked to the same subsystem. Certificates won't issue until their prerequisites are met.