Who does what in completions: roles and responsibilities

Completions managers, contractors, inspectors, commissioning engineers and the client each own part of the record. Clear roles are how nothing falls between them.

· 7 min read

Share
Illustration of a project team: manager, contractor, inspector, commissioning and client

Most completions problems aren't about software or forms. They're about nobody being sure whose job something is. A punch item with no responsible company never closes. A check sheet nobody owns is never signed. This lesson sets out who does what on a typical project.

Completions manager

  • Owns the completions system, the system breakdown and the check sheet matrix.
  • Agrees punch categories and certificate prerequisites with the client.
  • Runs the weekly completions meeting and publishes the reports.
  • Spots gaps early: subsystems falling behind, overdue punches, unsigned sheets.
  • Assembles certificates and the turnover dossier.

Contractors and subcontractors

  • Complete and sign construction (A) check sheets as each tag is finished.
  • Fix punch items assigned to them and mark them ready with a photo.
  • Supply vendor documents, test records and as-builts on time.

QA/QC inspectors

  • Verify check sheets and witness tests.
  • Raise punch items and NCRs with clear descriptions and photos.
  • Verify fixes and close items, or reject them with a reason.

Commissioning engineers

  • Confirm each subsystem is ready before testing it.
  • Carry out and record pre-commissioning (B) and commissioning (C) checks.
  • Raise punches found during testing, and sign ready for start-up.

Client or owner

  • Agree the rules: categories, certificates, dossier contents.
  • Witness hold points and accept certificates.
  • Bring operations and maintenance staff in early, so they learn the plant and spot issues.

Making roles real in the software

Give each person a role and a company. Assign every punch to a company and every check sheet to the company doing the work. Use the role's rights to decide who can verify, close and sign. When a contractor logs in, they should see their own list and nothing else.

If an item has no owner and no date, it isn't on anyone's list. It's on everyone's conscience.

Next in the academy

With roles clear, the next lesson covers setting up a project's completions properly, from the system breakdown to the check sheet matrix.