Installation progress by the metre, with weighted rules of credit

Import your engineering schedules from CSV and SureCon tracks every cable, line and piece of equipment through its weighted steps: pulled, terminated, tested. Progress rolls up by quantity, by discipline, schedule and subsystem, so you report what's really built.

Free forever · No credit card · Unlimited users

What you get

Six schedule types

Cable, raceway, piping lines, HVAC duct, mechanical equipment and instruments.

Rules of credit

Each step carries a weight; for cable, pulled 40 %, each end terminated 20 %, tested 20 %.

Quantity-weighted

A 300 m cable counts for more than a 3 m one, so the percentage means something.

Bulk updates

Select rows, mark a step done, and the progress updates.

Re-import safely

Re-importing updates rows by reference; columns named after a step import progress too.

Zoom in

Move from the whole project to a system, subsystem or single tag.

How it works

  1. 1

    Import

    Upload each schedule as CSV.

  2. 2

    Report

    Mark steps done as the work happens.

  3. 3

    Roll up

    See progress by discipline, schedule and subsystem.

  4. 4

    Hand over

    Installation progress feeds the subsystem table and dashboard.

Questions

What are rules of credit?

Rules of credit split an activity into weighted steps, so partial work earns partial progress. For example, a cable might earn 40 % when pulled, 20 % for each end terminated and 20 % when tested.

Can I change the weights?

SureCon ships with standard weights per schedule type. Contact us if your contract uses different ones.

Which file format do I need?

CSV, with a reference column and your quantities. Columns named after a step import that step's progress.