Rules of credit: measuring cable and piping progress honestly
“The cables are 80 % done” means nothing until you say what done means. How weighted steps turn metres pulled, terminated and tested into progress you can defend.
· 6 min read

Every progress meeting has the same argument. The electrical contractor says the cable schedule is 80 % complete. The commissioning lead says almost nothing is ready to test. Both are right, because they're counting different things.
Rules of credit end the argument. They split each item into the steps that matter, give each step a weight, and add up only what has actually been done.
What a rule of credit looks like
For a power cable, a common split is: pulled 40 %, from-end terminated 20 %, to-end terminated 20 %, tested 20 %. A cable that's pulled but not terminated has earned 40 %. A cable that's pulled, terminated at both ends and tested has earned 100 %.

Weight by quantity, not by count
Counting cables treats a 5 m jumper the same as a 250 m feeder. Weighting by length (or by weight for steel, by inch-dia for piping) gives a truer picture of the work done and the work left. The same applies when you roll up: a subsystem's progress is the quantity-weighted progress of everything in it.
Typical splits by discipline
- Cable: pulled 40, from end terminated 20, to end terminated 20, tested 20.
- Raceway (tray and conduit): installed 70, supported and bonded 20, labelled 10.
- Piping lines: spools fabricated 30, erected 35, welded and NDE 20, pressure tested 15.
- HVAC duct: installed 60, insulated 20, tested and balanced 20.
- Mechanical equipment: set 50, levelled and aligned 30, grouted and bolted 20.
- Instruments: installed 40, hooked up 30, calibrated 15, loop checked 15.
Agree the splits with your client before work starts and write them into the progress procedure. Changing them halfway through a project makes every previous report wrong.
How SureCon does it
Import your cable, raceway, piping, HVAC, equipment and instrument schedules from the spreadsheets you already have; columns named after a step import the progress you've already recorded. Select rows and mark a step done. SureCon works out quantity-weighted progress by discipline, by schedule, by system and by subsystem, so the progress meeting starts from the same numbers for everyone.