Raise and answer technical queries (TQs)

Ask engineering a question, get a recorded answer, and stop work waiting on emails.

3 min
Technical queries with their status
Technical queries with their status, in a sample project.
  1. 1

    Raise a TQ

    Engineering & documents → Technical queries → Raise TQ. Write a clear subject and question, choose who it's addressed to, the discipline and a 'response needed by' date.

  2. 2

    Set the priority

    Choose Urgent (work is held up) only when the crew is actually stopped. Urgent open TQs are counted at the top of the list.

  3. 3

    Link it

    Add the subsystem, tag and drawing number so the answer can be found later from any of them.

  4. 4

    Answer it

    The person it's addressed to writes the response on the TQ. It then shows as Answered, not closed.

  5. 5

    Accept and close, or reopen

    The person who raised it reads the answer and closes it, or reopens it with a comment if the answer doesn't settle the question.