Plan and record commissioning activities

Keep a register of commissioning activities per system, with procedures, planned dates and results.

3 min
The commissioning activities register
The commissioning activities register, in a sample project.
  1. 1

    Open the register

    Turnover → Commissioning in the project menu (switch the Commissioning module on in Setup if you don't see it).

  2. 2

    Add activities

    Add each activity with its procedure number, subsystem and planned start: loop checks, motor runs, flushing, function tests, performance tests.

  3. 3

    Check readiness first

    Before an activity starts, check the subsystem's mechanical completion certificate, open A punches and preservation status on its page.

  4. 4

    Record the result

    Write the result and remarks, attach the signed test record, and update the status. Raise punches for anything found.