Handover

Certificates and turnover packages

From mechanical completion to final acceptance, worked out from your records.

6 min
Handover certificates by subsystem
Handover certificates by subsystem, in a sample project.
  1. 1

    Check readiness

    Turnover → Handover lists each subsystem's certificates (MC, RFC, RFSU, handover, final acceptance) with their readiness checks.

  2. 2

    Clear what's missing

    Each check says what's left: unsigned check sheets, open top-category punch items, open NCRs or documents not yet accepted.

  3. 3

    Sign in order

    Each certificate needs the previous one signed. The sign-off chain signs in order; once complete it stays signed.

  4. 4

    Generate the package

    Generate package downloads a PDF with the certificate, signatures, asset register, check sheets, deliverables, inspections, NCRs and drawings.