The completions manager's checklist, phase by phase

A practical checklist from project start to final handover: what to set up, what to watch and what to sign at each stage.

· 8 min read

Share
Illustration of a phase-by-phase checklist from setup to handover

This checklist brings the whole academy together. Print it, adapt it to your project, and work through it phase by phase.

Before construction starts

  • System breakdown agreed and loaded.
  • Tag register imported and reconciled against engineering lists.
  • Check sheet matrix defined per tag type and phase.
  • Punch categories and certificate rules signed off.
  • Dossier index agreed with the client.
  • Roles, companies and people set up; first users trained on site.

During construction

  • A sheets signed as tags are finished; unsigned backlog reviewed weekly.
  • Punches raised on a phone with photos, company and due date.
  • Hold points released in the system, with witnesses booked ahead.
  • Preservation routines running and recorded.
  • Vendor documents and test records tracked against due dates.
  • Weekly completions meeting run from the dashboard.

Approaching mechanical completion

  • Walkdowns per subsystem with construction, commissioning and the client.
  • A punches closed and verified.
  • Test packs released; IR and continuity tests recorded.
  • Mechanical completion certificates raised as prerequisites are met.

Commissioning

  • Readiness checked per subsystem before work starts.
  • B and C sheets recorded; punches from testing raised and tracked.
  • Ready for commissioning and ready for start-up certificates signed.

Handover and close-out

  • Turnover dossier generated per system and checked against the index.
  • Remaining B punches agreed with owners and dates.
  • Preservation handed over to maintenance.
  • Contract close-out lists completed per contractor.
  • Lessons learned recorded and shared.

Keep learning

The SureCon help center has step-by-step guides for each of these tasks, and role playbooks for completions managers, inspectors, contractors, commissioning leads and owners. The fastest way to practise is to open a sample project and work through a subsystem from first sheet to handover.