Completions KPIs that matter (and the ones that don't)
The handful of measures that predict whether you'll hand over on time, how to read them and how to avoid vanity numbers.
· 7 min read

A completions dashboard can show hundreds of numbers. Only a few tell you whether you'll make handover. Here they are, with how to read each one.
1. Punch burndown: raised versus closed
Plot punches raised and closed each week. Early on, raised is higher, which is fine: you're finding things. As milestones approach, closed must overtake raised. If it doesn't, the milestone will slip, whatever anyone says.
2. Open A punches per subsystem due for a milestone
The overall punch count hides what matters. What blocks mechanical completion is the A punches on the subsystems due next. Track those by name.
3. Check sheet progress by phase
Signed sheets against total, split by A, B and C and by subsystem. A sheets lagging behind installation progress means paperwork is piling up.
4. Milestones achieved against plan
Count certificates signed against the plan, per week. It's the most honest measure of all, because each one has passed its prerequisites.
5. Age of open items
Average and oldest age of open punches, by company. Old items are usually stuck on something nobody has raised: a missing part, an unclear scope.
6. Verification backlog
Items marked ready but not yet verified. If this grows, inspectors are the bottleneck, not contractors.
Numbers to be careful with
- Total punch count: grows with good inspection; on its own it says little.
- Overall percent complete: easily dragged up by easy work; look at it by system.
- Reported progress: if it isn't calculated from records, it's an opinion.
In SureCon
The punch dashboard shows the weekly raised and closed chart, who items are waiting for, and the least complete subsystems. Progress is calculated from signed records with weights you set, and the report builder lets you create any other measure and email it on a schedule.