Completions for owners and clients: what to ask for
As the owner you'll live with the plant and its records for decades. What to require from contractors, and how to follow completions without micromanaging.
· 7 min read

Owners pay for completions twice: once in the contract, and again when a poorly documented plant is hard to run and maintain. Asking for the right things at the start costs little and pays back for the life of the asset.
Put it in the contract
- The system breakdown and who agrees it.
- Punch category definitions, with examples.
- Certificate prerequisites for each milestone.
- The dossier index and the format (digital, searchable, linked to tags).
- Access to the completions system for your team throughout, not just at the end.
Follow it without micromanaging
Ask for read access and look at three things weekly: the punch burndown, milestones achieved against plan, and the subsystems due next with their blockers. Witness your hold points in the system, and raise your own punches on walkdowns directly into the shared list.
Bring operations in early
Operators and maintainers spot things engineers don't: valves that can't be reached, labels that make no sense, missing drains. Invite them to walkdowns from mechanical completion onwards, and have their findings raised as punches like anyone else's.
At handover
- Accept systems one at a time, with their records.
- Accept remaining B punches only with owners and dates.
- Make sure preservation hands over cleanly to maintenance.
- Keep the records searchable by tag; you'll need them for decades.
In SureCon
Owners and outside parties can be given access or secure links, sign certificates electronically, and see the same dashboards as the contractor. Maintenance registers pick up where preservation stops.