Read the punch dashboard

Know at a glance what's open, who's holding it up and which subsystems are furthest behind.

3 min
The punch dashboard with weekly raised and closed
The punch dashboard with weekly raised and closed, in a sample project.
  1. 1

    Open it

    Reports → Punch dashboard in the project menu.

  2. 2

    Check the trend

    The weekly chart of punches raised and closed is the first thing to read. If raised stays above closed for weeks, completion will slip.

  3. 3

    See who's holding things up

    Items are split by who they're waiting for: the contractor, an inspector, or ready for verification. Chase the biggest pile first.

  4. 4

    Find the weakest subsystems

    Sort subsystems by Most open or Least complete. Those are the ones to walk down this week.