Measure progress and plot the S-curve

Earned against planned progress, worked out from check sheets, test packs and certificates.

4 min
Progress measured from completions records
Progress measured from completions records, in a sample project.
  1. 1

    Set the plan

    In Turnover tracker, give each subsystem its MC, RFC and RFSU dates. Each item is planned to ramp up over the six weeks before its milestone.

  2. 2

    Open Progress

    Turnover → Progress shows earned and planned progress today, the variance, the schedule performance index (SPI) and the S-curve.

  3. 3

    Find what's behind

    Break progress down by category, discipline and subsystem. Subsystems behind plan show their planned figure in red. Filter by system.

  4. 4

    Adjust the weights

    Admins set how much each category counts (A, B and C check sheets, test packs, certificates) under How it's measured.

  5. 5

    Report it

    Excel downloads the subsystem table and the S-curve points for monthly reports.