Find what's been missed with Gaps

One list of everything easy to miss before handover: tags with no sheets, items with no owner, overdue documents and more.

3 min Admins, inspectors and viewers. Contractors see their own items on the punch list instead.
The Gaps page listing what could be missed
The Gaps page listing what could be missed, in a sample project.
  1. 1

    Open Gaps

    Reports → Gaps in the project menu. Each card is one kind of gap, with how many there are and why it matters.

  2. 2

    Work through each card

    Open a card to see the items, oldest first. Click one to go straight to the tag, punch item, query or register and fix it there.

  3. 3

    What it checks

    Tags with no check sheets; punch items with no company or no due date; overdue punch items; check sheets started but untouched for two weeks; completed sheets not verified for two weeks; overdue handover documents; overdue preservation; and technical queries past their response date.

  4. 4

    Make it a weekly habit

    Go through Gaps before the weekly completions meeting. The goal is an empty list before each milestone.