Run piping test packs and weld maps

Build a test pack, track its welds to acceptance, and test, reinstate and close it.

5 min Anyone except viewers creates packs and records welds. Admins and inspectors sign off tests, close packs and delete.
Piping test packs and their readiness
Piping test packs and their readiness, in a sample project.
  1. 1

    Create the pack

    Test packs → New test pack. Give the pack number, subsystem, line numbers and isometrics, the test type and the design pressure. SureCon suggests the test pressure (1.5 × design for hydrotests, 1.1 × for pneumatic) before temperature correction.

  2. 2

    Add the welds

    Add welds and paste rows from your weld log: ISO, line, weld number, size, schedule, material, joint, shop or field, welder, WPS, date, visual, NDE method and result. Welds already on the map are updated, not duplicated.

  3. 3

    Record results

    Set visual and NDE results in the weld table. A rejected weld shows Repaired: use it once it's cut out and rewelded, and it goes back for inspection with its repair count.

  4. 4

    Tick the readiness checks

    Each stage lists what must be done first: limits marked on current P&IDs and isometrics, walkdown done, category A punch cleared, gauges calibrated, relief valve fitted, isolations, blinds, vents and drains, and the permit to work.

  5. 5

    Move it on

    Move to the next stage when the blockers are cleared. Record the test date, result and witnesses; an admin or inspector signs off Tested and Closed. Moving a pack back is always allowed.

  6. 6

    Browse weld maps

    Weld maps lists every weld on the project. Filter by state, NDE method, pack or welder, check welder repair rates and export to Excel.