Set up a project properly

Go through the Setup tabs once, in order, so every punch, sheet and report lands in the right place.

6 min Project admins.
Project setup with its tabs
Project setup with its tabs, in a sample project.
  1. 1

    Open Setup

    Project → Setup in the project menu. The tabs along the top are Systems, Companies, People, Categories, Punch list, Modules, Roles, Forms & workflows and Demo data. Work left to right the first time.

  2. 2

    Systems first

    Add your systems and subsystems, or import them from Excel. Everything else hangs off subsystems: tags, check sheets, punches, certificates and progress. Use the codes your client and schedule already use.

  3. 3

    Companies and people

    Add each contractor, vendor and the client as a company, then invite people and give each one a role and a company. Contractors only see what their company is assigned.

  4. 4

    Punch categories and settings

    Categories sets what A, B and C mean on this project (for example A before mechanical completion, B before handover). The Punch list tab adds punch groups and can show a responsible person field on punches.

  5. 5

    Switch modules on or off

    Modules hides what you don't use, so the menu stays short. You can switch a module back on later without losing anything.

  6. 6

    Roles, forms and workflows

    Roles lets you add custom roles with exactly the rights you want. Forms & workflows holds custom forms and approval steps. Leave both at their defaults until you know you need more.

  7. 7

    Try it with demo data, then clear it

    Demo data fills the project with sample records so you can practise. Remove it from the same tab before you go live.