What goes in a turnover package: a practical checklist
The turnover package is the proof that a system was built and tested right. A checklist of what to include, how to organise it, and how to stop it becoming a last-minute scramble.
· 5 min read

At handover, the client doesn't just take the keys. They take responsibility for a plant they didn't build, so they want proof it was built to design, tested and ready to run. That proof is the turnover package: one set of records per system or subsystem.
The checklist
- The completion certificate (MC, RFC, RFSU or handover) with its signatures.
- The tag list for the subsystem, with technical data.
- Construction (A), pre-commissioning (B) and commissioning (C) check sheets, signed and verified.
- The punch list, showing what's closed and what's allowed to stay open.
- Inspection records from the ITP: hold and witness point results.
- The NCR register for the subsystem, with dispositions and close-out.
- Test packs: pressure tests, insulation resistance, loop checks, calibration certificates.
- As-built drawings and redlines.
- Vendor documents: manuals, datasheets, spares lists and warranties.
- Training records where operators must be trained before handover.
Why packages run late
Most of the content already exists somewhere. The work is finding it: chasing a signature on a check sheet from six months ago, hunting for a calibration certificate in someone's inbox, or discovering that a vendor manual was never submitted. Left to the end, a package for one subsystem can take weeks.
Build it as you go
- Agree the package contents per system type at the start of the project.
- Track what each contractor and vendor owes as deliverables, with due dates.
- Accept or reject deliverables when they arrive, not at handover.
- Sign check sheets on site, when the work is done, so nothing needs chasing later.
- Watch readiness per subsystem, so gaps show up weeks before the certificate is due.
How SureCon helps
Each certificate in SureCon lists its readiness checks, worked out from the records: check sheets per phase, required documents accepted, open punch items and NCRs. When it's signed, Generate package downloads one PDF with the certificate, signatures, asset register, check sheets, deliverables, inspections, NCRs and drawings. You can also download free completion certificate templates from our templates page.